Earth Stability

Case Studies

Project:   Pohutakawa Road, Beachlands

Date:  October 2017 - January 2018

Client:  Private Client

 

ESL was engaged, through direct negotiation with the homeowner, to provide a full design and build solution following a large landslip to their clifftop property in 2017.

The completed project included the initial consultation, site investigation, detailed design, obtaining resource and building consents, carrying out complete construction of the solution and obtaining a code of compliance upon completion of the works. 

Following the initial consultation, ESL installed emergency temporary protection to the site to prevent any further loss of land, while a more permanent solution was developed.

Permanent works consisted of the following.

  • Construction of a 20m long tied-back timber pole retaining wall consisting of 6m deep 350mm diameter timber posts.
  • A continuous 300mm diameter waling beam with 8 No. 10m long ground anchors.  
  • The existing slip was re-contoured by hand then covered with 220m² of turf reinforcement matting overlaid with double twist rock fall mesh secured with 54 No. drilled and grouted soil nails.
  • To provide permanent dewatering of the slope, 7 No. 9 metre long bored horizontal drains were also installed.
  • The works were finished off with a 400mm x 400mm 20m long reinforced concrete capping beam and glass balustrade. 

The site had extremely restricted access down each side of the property and required us to work at a height of 20m over a vertical section of cliff above the sea below.  

ESL’s highly skilled technical team and specialist ‘one of a kind’ restricted access plant, enabled us to expertly carry out the works, placing paramount importance on the health and safety of employees and residents and the sensitive costal landscape. 

Work was completed on time, to budget and exceeded client’s expectations

Click on any of the thumbnail images for a larger view.

Contact Us about your project

« More Case Studies

Completed capping beam

Completed capping beam

Completed slip repair

Completed slip repair

Completed slip repair 2

Completed slip repair 2

Completed slip repair 3

Completed slip repair 3

Drilling of the pile holes

Drilling of the pile holes

Installation of retaining wall poles

Installation of retaining wall poles

Installation of the waling beam

Installation of the waling beam

Mobilising of equipment to the slip site

Mobilising of equipment to the slip site

Pohutakawa landslip

Pohutakawa landslip

Soilnail and slope reinforcement system

Soilnail and slope reinforcement system

Temporary protection

Temporary protection